Falcon Creek Manufacturing - Progress from intake through sign-off
✓
Engagement Accepted
Intake2024-11-15Client acceptance and onboarding. Risk profile assessed.
✓
Audit Planning Begins
Phase 12024-12-01Risk assessment, materiality calculation ($500K), preliminary analytical procedures.
✓
Planning Complete
Phase 12024-12-15Audit plan finalized. Procedures identified. Team assigned.
✓
Fieldwork Begins
Phase 22025-01-15Controls testing and substantive procedures commence. 70+ items tested.
✓
Fieldwork Complete
Phase 32025-01-31All evidence compiled. Financial statements finalized.
●
EQR In Progress
Phase 32025-02-07Concurring partner review. Final approval pending.
INTAKE
1 day
PHASE 1
51 days
PHASE 2
17 days
PHASE 3
In Progress